PRJ: Error Message Indicating Nonworking Time When Moving a Task (178310)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for the Macintosh 4.0
- Microsoft Project for Windows 4.0
This article was previously published under Q178310 SYMPTOMS
In Microsoft Project, when you move a task to a new date, you may see a
message indicating the day is nonworking, even though the following
condition(s) are true:
- Case A: The day is a working day for an assigned resource's
calendar.
- Case B: The task is assigned duration in Elapsed Time Units.
CAUSECase A
This problem occurs when a day in the project calendar is set as Nonworking
(Saturday for example), and that same day in the resource calendar for the
resource assigned to the task is set as Working.
Case B
This problem occurs when you move a task that is assigned Elapsed Duration
to a day that is set as Nonworking in the project calendar.
WORKAROUND
To work around this problem, when the message appears, click to select the
Don't tell me about this again check box, and then click OK. Then, move the task again as needed.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbbug kberrmsg kbpending KB178310 |
---|
|