PRJ: Task Start/Finish Different from Assignment Start/Finish (178187)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q178187 SYMPTOMS
In Microsoft Project, a task's Start and Finish dates may be different
than the Resource Assignment's Start and Finish dates for the resource
assigned to that task.
CAUSE
This behavior occurs when the resource assigned to a task uses a calendar
with different working times than the Project Calendar, and the task type
is Fixed Duration. The task is scheduled by the Project calendar, and the
Resource Assignment is scheduled by the Resource Calendar.
WORKAROUND
To work around this problem, change the Task Type to Fixed Units or Fixed
Work by following these steps:
- Using the right mouse button, right-click the task and then click
Task Information on the shortcut menu.
- Click the Advanced tab.
- In the Task Type list, click to select Fixed Units, or
Fixed Work, and then click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
MORE INFORMATION
For example, assign a task with a resource using the 24 Hours Calendar to
start at 5:00 PM on Friday and finish at 1:00 AM on Saturday. If you change
the Task Type to Fixed Duration, the task's Start time becomes 8:00 AM on Monday and the Finish time becomes 5:00 PM on Monday. The resource assignment's Start time remains 5:00 PM on Friday and the Finish time remains at 1:00 AM Saturday as expected.
NOTE: Similar behavior can also occur when a resources Work contour is modified, such as when a Delay or Leveling Delay is assigned to the Resource Assignment.