PRJ98: Changing Fixed Work Tasks Duration Results in Wrong Value (177478)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q177478 SYMPTOMS
In Microsoft Project 98, when reducing a task's duration, the duration may
not change to the value you enter. Instead, it may change back to the
original value or to a value between the new duration and the original
duration.
CAUSE
This problem occurs if all of the following conditions are true:
- The task has a resource assigned to it.
- The task type is Fixed Work.
- The task is greater than 0 percent complete.
- After making the task a successor to another task, Microsoft Project
automatically split the task so the remaining work was scheduled
after the predecessor finish date.
- After making the predecessor/successor relationship, you changed the
duration to a larger value.
WORKAROUND
To work around this problem, follow these steps:
- Remove the predecessor/successor relationship between the two tasks.
To do this, select the tasks and click Unlink Tasks on the
Edit menu.
- On the task that was the successor, enter the duration to the value
you want.
- Re-create the predecessor/successor relationship between the two
tasks. To do this, select the tasks and click Link Tasks on
the Edit menu.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
MORE INFORMATION
If you are changing duration on a Fixed Work task, Microsoft Project
spreads the scheduled work or remaining work across the new duration. When
increasing duration to a task that Microsoft Project has split, it
correctly spreads the remaining work across the new duration but does not
do this when decreasing the duration. Microsoft Project only splits the
remaining work for a task because of a task relationship.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB177478 |
---|
|