PRJ98: Total BCWP May Not Show Correct Timephased BCWP (176309)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q176309 SYMPTOMS
In Microsoft Project 98, if you enter a percent complete value for a task
prior to the start date of that task, total Budgeted Cost Of Work Performed
(BCWP) for the task will not correctly show the total of timephased BCWP
displayed in the timescale.
CAUSE
You are allowed to enter timephased % Complete values so that you can
accurately reflect the progress on your schedule. The problem described in
this article only occurs when you enter timephased % Complete values prior
to the start date of the task. The total BCWP for the task will only show
the BCWP that occurs after the start date of the task.
WORKAROUND
To work around this behavior, set the Actual Start of the task to the first
date that any work is done on the task. To do so, follow these steps:
- On the View menu, click Task Usage.
- On the View menu, click Table, and then click
Tracking.
- Select the task for which the timephased % Complete values are
prior to the start date of the task.
- In the Actual Start field for the task, enter the first date
that any work is done on the task.
- Edit the timephased % Complete values to reflect when the
other work was performed.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB176309 |
---|
|