PRJ: Circular Relationship Error When Indenting Task (176293)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q176293 SYMPTOMS
In Microsoft Project, if two tasks are linked in a predecessor/successor
relationship and you indent the successor to make it a subtask and the
predecessor of a summary task, you may receive the following error message:
This outline change would create a circular relationship.
CAUSE
This problem occurs when the predecessor task has a cross-project link as a
predecessor and the task you are trying to subordinate is its successor. For example, let's say you have two tasks (A and B). They are linked by a Finish to Start relationship and Task A has a cross-project link to a task in another project. If you indent task B under Task A, you will receive this error message.
WORKAROUND
To work around this problem, remove the predecessor and successor link between the tasks and then indent the task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 2/20/2004 |
---|
Keywords: | kbbug kbpending kbusage KB176293 |
---|
|