PRJ98: Can Not Change Dates on Assignments That Have Zero Work (175465)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q175465 SYMPTOMS
In Microsoft Project 98, if you have an assignment that has zero work or zero units, you will not be able to set the Start Date or the Finish Date for the assignment.
WORKAROUND
To work around this problem, follow these steps:
- On the View menu, click Gantt Chart. (Or, on the
View menu, click More Views. In the More Views
dialog box, click Task Sheet and then click OK).
- On the Window menu, click Split.
The Task Form view will appear in the bottom pane. - Click anywhere in the Task Form.
- On the Format menu, point to Details, and then click
Resource Schedule.
The Delay and Leveling Delay columns will appear in the
Task Form. To move the assignment to a date that occurs after
the task start date, type a value in either the Delay or the
Leveling Delay column.
NOTE: If you change the Start Date or the Finish
Date, both Leveling Delay and Delay will be
removed.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kbusage KB175465 |
---|
|