PRJ98: Duration Not Calculated When Entering Dates for a Task (174345)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q174345 SYMPTOMS
In Microsoft Project, when you enter dates for an existing task, the
duration may not be calculated based on the dates entered.
CAUSE
This behavior occurs if the task is a milestone. Since the duration of a
milestone is zero days, it will disregard one of the two dates you enter.
WORKAROUND
To calculate the duration, follow the appropriate steps for your situation:
Microsoft Project 98- Select the task in Gantt Chart view.
- On the Project menu, click Task Information.
- In the Task Information dialog box, change Duration to
1d.
- Click OK.
- Repeat Steps 1 and 2.
- In the Task Information dialog box, re-enter the start and
finish dates for the task. You must re-enter the dates even if one
of them is correct.
- Click OK.
For Microsoft Project 4.0, 4.1, 4.1a- Select the task in Gantt Chart view.
- On the Insert menu, click Task Information.
- In the Task Information dialog box, change Duration to
1d.
- Click OK.
- Repeat Steps 1 and 2.
- In the Task Information dialog box, re-enter the start and
finish dates for the task. You must re-enter the dates even if one
of them is correct.
- Click OK.
Microsoft Project 3.0 and 3.0a- Select the task in Gantt Chart view.
- On the Edit menu, click Form.
- In the Task Edit Form dialog box, change Duration to
1d.
- Click OK.
- Repeat Steps 1 and 2.
- In the Task Edit Form dialog box, re-enter the start and
finish dates for the task. You must re-enter the dates even if one
of them is correct.
- Click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbbug kberrmsg kbpending KB174345 |
---|
|