PRJ98: Microsoft Project Takes a Long Time to Save Baseline (173169)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q173169 SYMPTOMS
In Microsoft Project 98, if you save a baseline it may take a long time and
Project appears to stop responding (hang).
CAUSE
Microsoft Project may take a long time to save a baseline because it
calculates a large amount of data to set baseline fields. When a baseline
is saved, baseline values for all tasks are rolled up to summary tasks and
all resource assignment information is rolled up to resource baseline
fields. Microsoft Project now includes timescaled data associated with each
task and each resource. This timescaled data includes a large amount of
information, which causes significantly more calculations than previous
versions.
STATUS
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
| Modification Type: | Major | Last Reviewed: | 10/17/2002 |
|---|
| Keywords: | kbbug KB173169 |
|---|
|