PRJ: Setting Task to 0% or 100% Complete Updates Resource Status (172893)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q172893 SYMPTOMS
When you set a task to 0% or 100% complete, the actual work will be
set to 0 hours (0h) or the total amount of work, even though you cleared the "Updating task status updates resource status" check box on the Calculation tab in the Options dialog box. (On the Tools menu, click Options.)
CAUSE
This problem occurs because Microsoft Project recalculates a task set to 0% or 100% complete and updates the status of the task. In contrast, Microsoft Project 95 only recalculates a task set to 100% complete.
Modification Type: | Major | Last Reviewed: | 10/29/2003 |
---|
Keywords: | kbbug kbfix kbusage KB172893 |
---|
|