PRJ: BCWP for Resource Assignment Different from BCWP for Task (172783)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q172783 SYMPTOMS
The Budgeted Cost of Work Performed (BCWP) for a resource assignment does not match the BCWP for a task if the resource uses multiple cost rates.
CAUSE
This problem occurs when a resource has multiple cost rates. In this case, an average of the cost rates will be used to calculate BCWP rather than individual cost rates. This will cause the values of the BCWP of the resource assignment to differ from the BCWP task for the task.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.