PRJ: Summary Task Hides Previous Column After Linking (172736)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q172736 SYMPTOMS
If you paste link a project summary task into another application, such as
Microsoft Excel, and you clear the Project Summary Task option on the View tab (click Options on the Tools menu) the name of the task will appear incorrectly in the other application. For example, if you are using the default columns in Microsoft Project, the name of the summary task will span across the Indicator column and the Name column, hiding the data in those columns.
WORKAROUND
To work around this problem when linking to the summary task from another
application, follow these steps:
- In Microsoft Project, click Options on the Tools
menu.
- Click the View tab.
- Under Outline Options, click to select Project Summary
task.
- Click OK.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/29/2003 |
---|
Keywords: | kbbug kbnofix KB172736 |
---|
|