PRJ98: Unlinking Task Results in Removal of All Links (172729)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q172729

SYMPTOMS

In Microsoft Project 98, if you select a task and then unlink the task, all predecessor and successor tasks (links) will be deleted. This applies to external predecessor and successor tasks as well as normal tasks. For example, if you select a task and then click Unlink Tasks on the Edit menu, all tasks linked to the task will be unlinked in both the source project and the active project.

RESOLUTION

To remove a predecessor or successor task, unlink the predecessor or successor task rather than the external predecessor or successor task.

Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB172729