PRJ98: BCWS for Expanded Inserted Project Shows $0.00 (172722)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q172722

SYMPTOMS

When you expand an inserted project, the Budgeted Cost of Work Scheduled (BCWS) changes to $0.00.

CAUSE

This problem occurs when you save the baseline for the inserted project summary task before you expand the inserted project.

RESOLUTION

To resolve this problem, expand the inserted task and then save the baseline for the inserted project summary.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB172722