PRJ: Paste Linked Date Field Different from Source Date Field (171395)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q171395 SYMPTOMS
Paste linked date fields between tasks may not match even after you force a recalulation of the project.
CAUSE
By design, Microsoft Project does not recalculate linked date fields if a
task relationship, such as a Finish to Start relationship is assigned to
the project. However, if there is no task relationship assigned to the
project, then Microsoft Project 98/2000 recalculates the date field to be
equal to the source field. In contrast, in earlier versions of Microsoft
Project the same date appears in both fields when you recalulate the
project.