PRJ: Start Date Changes After Adding Delay, Actual Work (171055)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q171055 SYMPTOMS
If you assign a delay to a resource and you then enter actual work values
before the delay period, the start date of the task will change.
CAUSE
Microsoft Project will change the start date of the task in order to
preserve the amount of the delay for a resource.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
MORE INFORMATION
If a resource has been assigned a delay, then Microsoft Project will
preserve the delay for that resource. If you enter actual work that occurs
before the delay period, Microsoft Project will change the start date.
Modification Type: | Major | Last Reviewed: | 10/28/2003 |
---|
Keywords: | kbbug kbpending kbusage KB171055 |
---|
|