PRJ: Complete Indicator Missing from 100% Completed Task (170716)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows

This article was previously published under Q170716

SYMPTOMS

A task that is set to 100% complete does not show the complete indicator next to the task.

CAUSE

This behavior occurs when you set a task to 100% complete and then change the Actual Finish date to NA. Although the task remains 100% complete, the complete indicator will be removed.

WORKAROUND

To work around this problem, and show the complete indicator for the task, do either of the following:
  • Re-enter the task as being 100% complete.

    -or-

  • Enter an Actual Finish date for the task.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbprb kbusage KB170716