PRJ: Can't Link Tasks by Selecting Resource Assignment Row (170244)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows

This article was previously published under Q170244

SYMPTOMS

You cannot link tasks together in task usage view by selecting the resource assignment row for the task.

CAUSE

Because tasks are linked together on a task to task row basis, you cannot select the assignment row to create a link between tasks.

RESOLUTION

To create a relationship between tasks, select the task row and then create the link.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kbpending kbusage KB170244