PRJ98: First Assignment to a Task Not Calculated Correctly (170241)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q170241 SYMPTOMS
In Microsoft Project 98, when you assign a resource to a task that has a
percent complete, the resource will be assigned work for the total duration
of the task. For each subsequent resource, work will be calculated on the
remaining duration.
CAUSE
For the first assignment a resource is assigned to the total duration of
the task regardless of the percent complete.
WORKAROUND
To change the amount of work a resource is assigned, manually edit the
amount of work.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
MORE INFORMATION
For each additional resource the work will be calculated based on the
remaining duration of the task. To change the original resource assignment
manually edit the amount of work.
For example, let's assume you have a task that is 8 days long at 50% complete. When you assign a resource to the task, the work for the resource
will be 64 hours with 32 hours of actual work and 32 hours of remaining
work. When you assign a second resource to the task, the work for the first
resource will change to 48 hours (32 actual hours plus 16 hour or one-half
the remaining work). The work for the second resource will be 16 hours,
which is one-half the remaining work.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kbusage KB170241 |
---|
|