PRJ: Unlinking Task Doesn't Move Task Back to Original Dates (169727)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
This article was previously published under Q169727 SYMPTOMS
When you remove the link between tasks that have uncompleted work, the
tasks do not move back to their original Resume date.
CAUSE
This problem occurs when you reschedule the uncompleted work. Microsoft Project can only store one Resume date per task. When you reschedule uncompleted work for a task, the new date is placed in the Resume field. As a result, you cannot move the task back to the original Resume date.
WORKAROUND
To work around this problem, manually move the task back to the original date.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.