PRJ98: Changed Baseline Values in Usage View not Updated (169237)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q169237

SYMPTOMS

When you attempt to update the Baseline Work or Baseline Cost in the right pane while you are in Task Usage view, they are not updated. Instead, the Budgeted Cost of Work Scheduled (BCWS) and the Schedule Variance (SV) are updated.

WORKAROUND

To work around this problem and update the Baseline Work or the Baseline Cost of a task, use the Baseline Table. To do this,

  1. On the View menu, point to Table, and then click More Tables.
  2. In the More Tables dialog box, click Baseline, and then click Apply.
You can now update the Baseline Cost or Baseline Work values for a task.

Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbprb kbusage KB169237