PRJ98: Changed Baseline Values in Usage View not Updated (169237)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q169237 SYMPTOMS
When you attempt to update the Baseline Work or Baseline Cost in the right pane while you are in Task Usage view, they are not updated. Instead, the Budgeted Cost of Work Scheduled (BCWS) and the Schedule Variance (SV) are updated.
WORKAROUND
To work around this problem and update the Baseline Work or the
Baseline Cost of a task, use the Baseline Table. To do this,
- On the View menu, point to Table, and then click
More Tables.
- In the More Tables dialog box, click Baseline, and then
click Apply.
You can now update the Baseline Cost or Baseline Work values for a task.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbprb kbusage KB169237 |
---|
|