TMGR: How to Change Start Date for Team Plan (159808)
The information in this article applies to:
This article was previously published under Q159808 SUMMARY
No tasks in a Microsoft Team Manager plan can be scheduled before the start
of the team file. If a task must start before the current schedule's start
date, you must modify the schedule's start date. To do so, follow these
steps: - On the Tools menu, click Options.
- In the Options dialog box, click the Calculation tab.
- Under Schedule Start Date, change the date to at least as early as the
earliest task in your schedule.
- Click OK.
REFERENCES
For additional information about this topic, please see the following
article in the Microsoft Knowledge Base:
149814 No Message for Task Link Prior to Schedule's Start Date
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | kbhowto KB159808 |
---|
|