TMGR: How to Change Start Date for Team Plan (159808)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q159808

SUMMARY

No tasks in a Microsoft Team Manager plan can be scheduled before the start of the team file. If a task must start before the current schedule's start date, you must modify the schedule's start date. To do so, follow these steps:

  1. On the Tools menu, click Options.
  2. In the Options dialog box, click the Calculation tab.
  3. Under Schedule Start Date, change the date to at least as early as the earliest task in your schedule.
  4. Click OK.

REFERENCES

For additional information about this topic, please see the following article in the Microsoft Knowledge Base:

149814 No Message for Task Link Prior to Schedule's Start Date


Modification Type:MinorLast Reviewed:8/17/2005
Keywords:kbhowto KB159808