TMGR: Summary Task Information When Filtering (159797)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q159797

SUMMARY

When you use a filter in a team file, some information will be rolled up to the Summary level, but not all expected information will be rolled up.

MORE INFORMATION

The following fields will be rolled up to the Summary level and will only reflect information from the filtered tasks:
   % Complete
   Actual Work
   Remaining Work
   Total Work
   Unassigned Work
   Actual Cost
   Remaining Cost
   Total Cost
				
The Start and Finish fields, as well as the Actual Start and Actual Finish, for a Summary task will be blank when the view has a filter applied.

Baseline fields will retain the information that was set for the Summary task and will not be affected by the filtered tasks.

Modification Type:MinorLast Reviewed:8/17/2005
Keywords:KB159797