PRJ: Project Lag Uses Base Calendar Instead of Resource Calendar (159773)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 4.0
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q159773 SYMPTOMS
When you specify lag time to delay a task, the task may appear to be
incorrectly scheduled.
This behavior may occur when a resource assigned to a task has a different
calendar than the base calendar. At this point, the portion of the task
where the lag is scheduled is scheduled using the Base Calendar.
Microsoft Project uses the Base Calendar to schedule lag to avoid any
potential conflicts when scheduling multiple resources.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|