TMGR: Finish Date of Task Set to Current Date (159401)
The information in this article applies to:
This article was previously published under Q159401 SYMPTOMS
When a manager marks a task as complete in Microsoft Team Manager, the
Finish date for the task is set to the current date.
CAUSE
Microsoft Team Manager assumes that the Finish date of the task is the day
it is marked complete, not the day that work was last performed on the
task.
This will only happen if the manager is marking the task complete in
Microsoft Team Manager. If the people assigned to the tasks mark the task
complete in Microsoft Team Manager for team members and send updates to
their manager, the finish date of the task will be the date of the last
actual work entry.
WORKAROUND
The best option is to allow the team members to update the actual work on a
task by sending in Task Updates from the Team Manager for team members
program.
The workarounds for the manager are: - Mark tasks complete on the day they are actually completed.
-or-
- Reset the current date on the computer to the date of the last actual
work value, and then mark the task complete.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|