TMGR: Archive Can Include Tasks 100% And Status In Progress (153340)
The information in this article applies to:
This article was previously published under Q153340 SUMMARY
If the option "Include all tasks that are 100% complete" in the Archive
dialog box is selected, Microsoft Team Manager archives all records in the
time period you specify that are 100% complete, regardless of the task
status.
MORE INFORMATION
When you archive a file, the time period you specify is the first criteria
for selecting the tasks to archive to file and to delete from the current
team file. The second criteria is the status of "completed." If the option
to "Include all tasks that are 100% complete" is selected, the status is
ignored and the % Complete field is the new criteria. All the tasks in the
time period that are 100% complete are added to the archive file and
deleted from the team file.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|