TMGR: Summary Tasks Which Meet Filter Criteria Don't Appear (151970)
The information in this article applies to:
This article was previously published under Q151970 SYMPTOMS
If you apply a filter to a plan, any summary tasks that apparently fit the
criteria are not shown.
CAUSE
Microsoft Team Manager only tests nonsummary tasks when establishing a
filtered view. As a result, if a summary task fits the criteria, it is not
shown. However, if a subtask fits the criteria, its related summary task is
shown, whether or not it fits the criteria.
STATUS
This is by design.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|