TMGR: Conflict Symbol Displayed If Finish Date After 12/26/50 (151968)
The information in this article applies to:
This article was previously published under Q151968 SUMMARY
In Microsoft Team Manager, if the Finish date of a task is greater than or
equal to 12/26/2050 12:00am, the task is considered to have a conflict and
is displayed with a conflict symbol. Clicking the conflict symbol displays
the following message:
Team Manager cannot schedule this task either due to daily
limit constraints or because the schedule would exceed Team
Manager's scheduling limit of the year 2050.
MORE INFORMATION
Acceptable date values that can be entered in Date fields are between
1/1/1984 12:00am and 12/31/2050 11:59pm. However, task dates are
considered in conflict if they exceed 12/26/2050 12:00am.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | KB151968 |
---|
|