TMGR: Task Bars May be Inconsistent When Calculation Is Manual (151124)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q151124

SUMMARY

If calculation is set to manual and task bars are dragged to a new time frame, some of the remaining bars move while others do not. The bars that did not move do move to the correct locations when the schedule is recalculated, either manually or by setting calculation back to automatic.

MORE INFORMATION

Any bar that reflects entered data is updated immediately when that data is changed. If a bar is moved, all bars that use the changed data are updated. Any bar that uses calculated data, such as start and finish dates, does not change until the schedule is recalculated and the new values are determined.

Modification Type:MinorLast Reviewed:8/17/2005
Keywords:KB151124