TMGR: Task Bars May be Inconsistent When Calculation Is Manual (151124)
The information in this article applies to:
This article was previously published under Q151124 SUMMARY
If calculation is set to manual and task bars are dragged to a new time
frame, some of the remaining bars move while others do not. The bars that
did not move do move to the correct locations when the schedule is
recalculated, either manually or by setting calculation back to automatic.
MORE INFORMATION
Any bar that reflects entered data is updated immediately when that data is
changed. If a bar is moved, all bars that use the changed data are updated.
Any bar that uses calculated data, such as start and finish dates, does not
change until the schedule is recalculated and the new values are
determined.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | KB151124 |
---|
|