TMGR: Actual Date Fields Store Only Date Data, Not Time (150671)
The information in this article applies to:
This article was previously published under Q150671 SUMMARY
The Actual Start and Actual Finish fields only store the date information,
instead of both date and time, like the Start and Finish fields. This can
result in confusion if the date columns are set to display the time in
addition to the date because the actual start time defaults to 12 AM (or
00:00) and the end time defaults to 11:59 PM (or 23:59).
MORE INFORMATION
Microsoft Team manager stores Actual Work for a time period. A time period
is a whole day, and in this context, is a 24 hour period starting at
midnight and ending the following midnight. The Actual Work is stored in
hours as expected.
Additionally, when a task is completed, the schedule dates and times are
set to the actual dates and times.