SYMPTOMS

When you try to paste data into a non-editable cell, the paste fails, but no message is displayed explaining that the cell is non-editable.

STATUS

This behavior is by design.

MORE INFORMATION

Examples of non-editable fields in a task table include Start, Finish, %Complete, and Actual Work. Non-editable fields are displayed with a shaded background as a visual clue. These fields are calculated automatically from other field values. For example, the Actual Work in the Task Status view is the sum of the Actual Work of the people assigned to the task.