TMGR: No Priority Set On a Recurring Task Summary (149503)
The information in this article applies to:
This article was previously published under Q149503 SUMMARY
After creating a recurring task, the Priority field appears enabled on the
Task Properties form. However when you switch back to Task view, the
priority is not shown or editable. When you again view the Task Properties
form, the priority is reset the Medium.
MORE INFORMATION
To create a recurring task, first create a task in one of the Task
views. Then, on the Task Properties form, click the Recurring Task button.
In Team Manager, the Task Properties form is not updated until after the
Task form is closed and reopened. It looks as though you can edit the
Priority field for the task, but when you view the Task view again no
priority is set. This is because a summary task cannot have a priority.
Modification Type: | Minor | Last Reviewed: | 8/17/2005 |
---|
Keywords: | KB149503 |
---|
|