TMGR: No Priority Set On a Recurring Task Summary (149503)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q149503

SUMMARY

After creating a recurring task, the Priority field appears enabled on the Task Properties form. However when you switch back to Task view, the priority is not shown or editable. When you again view the Task Properties form, the priority is reset the Medium.

MORE INFORMATION

To create a recurring task, first create a task in one of the Task views. Then, on the Task Properties form, click the Recurring Task button. In Team Manager, the Task Properties form is not updated until after the Task form is closed and reopened. It looks as though you can edit the Priority field for the task, but when you view the Task view again no priority is set. This is because a summary task cannot have a priority.

Modification Type:MinorLast Reviewed:8/17/2005
Keywords:KB149503