PRJ4: Restart Causes Standard Rate to Calculate on 8-Hour Day (138689)
The information in this article applies to:
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q138689 SYMPTOMS
The default standard and overtime rates change each time you restart
Microsoft Project if the Hours Per Day and Hours Per Week settings are changed to something beside the default of 8 hours and 40 hours and your rates are specified as days or weeks.
CAUSE
This problem occurs because Microsoft Project is recalculating the standard
and overtime rates using the original 8 hours per day and 40 hours per week
even though the defaults have been changed.
RESOLUTION
To prevent the recalculations from occurring, change the default hours per
day to 8 and the hours per week to 40.
NOTE: This problem does not affect rates associated with existing resources. The default standard and overtime rates are used only to determine a newly created resource's rates.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/7/2003 |
---|
Keywords: | kbbug kbpending kbusage KB138689 |
---|
|