PRJ4: Restart Causes Standard Rate to Calculate on 8-Hour Day (138689)



The information in this article applies to:

  • Microsoft Project for Windows 4.0
  • Microsoft Project for the Macintosh 4.0

This article was previously published under Q138689

SYMPTOMS

The default standard and overtime rates change each time you restart Microsoft Project if the Hours Per Day and Hours Per Week settings are changed to something beside the default of 8 hours and 40 hours and your rates are specified as days or weeks.

CAUSE

This problem occurs because Microsoft Project is recalculating the standard and overtime rates using the original 8 hours per day and 40 hours per week even though the defaults have been changed.

RESOLUTION

To prevent the recalculations from occurring, change the default hours per day to 8 and the hours per week to 40.

NOTE: This problem does not affect rates associated with existing resources. The default standard and overtime rates are used only to determine a newly created resource's rates.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kbpending kbusage KB138689