Schedule+ Tasks: Duration and Estimated Effort (130426)



The information in this article applies to:

  • Microsoft Schedule+ for Windows 7.0

This article was previously published under Q130426
The Duration field on the To Do tab and the Estimated Effort field on the Status tab of the Task dialog box can appear to present the same information.

The Duration field on the To Do tab represents the time between when the task starts and when it is finished. The Estimated Effort field on the Status tab of the Task dialog box represents how much work will actually be performed on the task.