PRJ: How to Display Summary Tasks on the Calendar View (114783)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q114783 SUMMARY
When you display the Calendar view, Summary tasks are not shown by default. This article describes how to display Summary tasks in Calendar view.