Percentages Show Incorrectly when Using Dates in Pie Chart (114544)
The information in this article applies to:
- Microsoft Works 3.0
- Microsoft Works 3.0a
This article was previously published under Q114544 SYMPTOMS
Works pie charts that use cell contents that are dates for the 1st Data
Labels and percentages for the 2nd Data Labels will have incorrect values
for the percentages.
WORKAROUND
To get the correct percentages for the 2nd Data Labels in the pie chart,
enter the dates for the 1st Data Labels as text in the spreadsheet. The
dates can be entered as text by starting the entry with a quotation mark
(") (that is, "1/5/94 or "January).
The incorrect percentages are generated when Works takes the numerical
value of the date (that is, 34459 for 5/5/94) and multiplies it with the
first percentage that is generated from the data.
Modification Type: | Major | Last Reviewed: | 9/26/2003 |
---|
Keywords: | KB114544 |
---|
|