Recurring Task Disappears When Draw Object Attached to Summary (113608)
The information in this article applies to:
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q113608 SYMPTOMS
In Microsoft Project, when you attach a drawing object to a summary
recurring task, the drawing object disappears.
CAUSE
This behavior occurs when the Hide Bar field for the summary recurring task contains the value Yes. If a task does not display a task bar on the Gantt Chart, the drawing object you attach to the task is not displayed.
Note that this behavior is true for any task, but is most evident when you
attach a task to a summary recurring task because the task bar is hidden by
default. Additionally, it is more difficult to set the Hide Bar field value for a recurring task summary because the Information button displays the Recurring Task Information dialog box, and there is no Hide Task Bar option in this dialog box.
WORKAROUND
To display a drawing object attached to a summary recurring task, or to
display the summary bar of a recurring task in the calendar view, do
the following:
- Select a field in the Duration column.
- On the Insert menu, click Insert Column.
- In the Field Name list, select Hide Bar, and click
OK.
- In the Hide Bar column for the summary task, enter
No.
Any drawing object already attached to the summary recurring task appears,
and any drawing object you attach to the summary recurring task will not
disappear.
REFERENCES
For more information about the Hide Bar (Task Field), choose the
Search button in Help and type:
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbprb kbusage KB113608 |
---|
|