PRJ: Actual Cost Not Reset When % Complete Reset (113541)
The information in this article applies to:
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for the Macintosh 3.0
This article was previously published under Q113541 SYMPTOMS
In Microsoft Project, when you reset a task's percent complete to zero, and
a fixed-cost resource has been assigned to that task, the resource's actual
cost for that task is not reset to zero .
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
| Modification Type: | Major | Last Reviewed: | 11/25/2003 |
|---|
| Keywords: | kbbug kbpending kbusage KB113541 |
|---|
|