PRJ: Task Scheduled for Nonworking Time Created as Milestone (113154)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q113154 SYMPTOMS
In Microsoft Project, if you create a task by dragging on the Calendar or the Gantt Chart, and you start dragging on a nonworking day and stop dragging on a nonworking day, the task is created as a milestone.
WORKAROUND
To avoid creating a milestone task when you create a task by dragging on a
view, do either of the following:
MORE INFORMATIONPlanningWizards do not appear when you edit your project in the Calendar view. Because of this, when you format and edit your project in this view, you receive the same results as when you format and edit your project in the Gantt Chart view with the PlanningWizards turned off.
REFERENCES
For more information about using the mouse to create and link tasks
on the Gantt Chart, choose the Search button in Help and type: