PRJ: Late Date Error Message Occurs with Single Task (108342)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q108342 SUMMARY
When you enter an Actual Start date that is later than the Scheduled Start date and the task has a Must Finish On Constraint, you may receive the following error message:
Late Date before Start Date in Task X.
In Microsoft Project 98, a constraint indicator will be shown in the
indicators field.
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbinfo kbusage KB108342 |
---|
|