PRJ: Definition of Microsoft Project Constraints (74978)
The information in this article applies to:
- Microsoft Project 2000
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q74978 SUMMARY
Each constraint type in Microsoft Project can be defined as a formula using
the following conventions:
ES = Early Start of the activity
LS = Late Start of the activity
EF = Early Finish of the activity
LF = Late Finish of the activity
SS = Scheduled Start of the activity
SF = Scheduled Finish of the activity
CD = Constraint Date
Modification Type: | Major | Last Reviewed: | 11/24/2003 |
---|
Keywords: | kbinfo kbother KB74978 |
---|
|