PRJ: Filter to Show Tasks Due to Finish on Specific Date (67169)
The information in this article applies to:
- Microsoft Project 98 for Windows
- Microsoft Project for Windows 95 4.1
- Microsoft Project for Windows 95 4.1a
- Microsoft Project for Windows 1.0
- Microsoft Project for Windows 3.0
- Microsoft Project for Windows 3.0a
- Microsoft Project for Windows 4.0
- Microsoft Project for the Macintosh 1.1
- Microsoft Project for the Macintosh 3.0
- Microsoft Project for the Macintosh 4.0
This article was previously published under Q67169 SUMMARY
In Microsoft Project you can create a filter to show only those tasks that
are due to be completed on a specific date (such as today).
Modification Type: | Major | Last Reviewed: | 11/25/2003 |
---|
Keywords: | kbhowto kbusage KB67169 |
---|
|