PRJ2000: Contour, Duration, and Units Change When Calendar Modified (242637)



The information in this article applies to:

  • Microsoft Project 2000

This article was previously published under Q242637

SYMPTOMS

In Microsoft Project, when you modify a project calendar, task calendar, or resource calendar, other information that is related to task scheduling and tracking may also change, for example:
  • Task percent complete
  • Contours of actual work for assignments
  • Task duration
  • Resource assignment units

CAUSE

This problem may occur when the following conditions are true:
  1. A task has a duration greater than 1-day.
  2. At least one resource is assigned to the task.
  3. You make a change to the task calendar, the project calendar, or the resource calendar that directly affects the task's schedule.
  4. The calendar modification coincides with a day on which actual work has already been recorded on the task.
  5. The calendar modification is for a day other than the Project Start Date.

WORKAROUND

To work around this behavior, follow these steps:
  1. Select the task.
  2. On the Project menu, click Task Information.
  3. Click the General tab.
  4. In the Percent Complete field, type 0 (zero).
  5. Type the original duration for the task and click OK.
  6. Repeat steps 1 through 3.
  7. Type the Percent Complete value for the task, and then click OK.
  8. Repeat steps 1 through 7 for each affected task.
NOTE: If you make calendar modifications to dates where actual work has already been recorded, you may permanently lose custom actual work contours that have been reported.

STATUS

Microsoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.

MORE INFORMATION

To preserve actual work that occurred on dates that you change to nonworking days, Microsoft Project evenly distributes that work across the actual duration of the task.

Consider the following example:
  • Task1 is five days in duration.
  • Resource1 is assigned with 100 percent units on the task.
  • The task is 60 percent complete and has an actual duration of three days.
  • You change day two of the task to a nonworking day, the duration to four days, and the actual duration to two days.
The eight hours of actual work that previously occurred on day two are divided evenly across the actual duration of the task, which gives 12 hours of actual work to each of the two days.

Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB242637