PRJ98: Finish Dates Are Too Early After Using Adjust_Dates Macro (193315)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q193315 SYMPTOMS
In Microsoft Project 98, when you use the Adjust Dates macro to reschedule tasks in a project that is scheduled from finish, the finish dates for all tasks in the project may be a day earlier than expected.
CAUSE
This behavior may occur when you run the Adjust_Dates macro and the
following conditions are true:
- One or more tasks are assigned a Must Start On constraint,
Must Finish On constraint, or Finish No Later Than
constraint.
- The project is scheduled to Start From Finish.
- When you run the Adjust_Dates macro, you enter a new project
finish date without a finish time in the Adjust Dates dialog
box.
If you do not include a finish time with the new project finish date, the
macro uses the Default Start Time setting (8:00 A.M. for example) on the Calendar tab in the Options dialog box.
WORKAROUND
To work around this behavior, when you run the Adjust_Dates macro, include the finish time with the new finish date, for example 9/25/98 5:00 PM.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB193315 |
---|
|