PRJ98: File Size Greatly Increases After Saving Baseline (187373)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q187373

SYMPTOMS

In Microsoft Project 98, when you save a baseline, the file size of a project may substantially increase, to as much as five times larger.

CAUSE

This problem may occur when the resource calendar is either:

  • Not based on the Standard calendar. -or-
  • Based on the Standard calendar that has been modified with a large number of calendar exceptions.
NOTE: The Standard calendar is the default calendar titled Standard when you create a new project. Its working time is 8:00 A.M .to 12:00 P.M. and 1:00 P.M. to 5:00 P.M. Monday through Friday. Saturday and Sunday are nonworking days.

Calendar exceptions are any customizations of the calendar, for example, making New Years Day and Christmas nonworking days, or creating a vacation of five days.

RESOLUTION

If you do not have costs assigned to resources in your project, this problem will be reduced if you install Microsoft Project 98 for Windows, Service Release 1 (SR-1).


To work around this problem, use the default Standard calendar.

STATUS

This problem was improved in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, please see the following article in the Microsoft Knowledge Base:

185102 PRJ98: How to Obtain and Install MS Project 98 SR-1


Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB187373