PRJ98: Usage Views Print Timescale Data in Wrong Cells (186072)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q186072 SYMPTOMS
In Microsoft Project 98, when you print the Task Usage or Resource Usage
views, data in the timescale may be printed in the wrong cells.
CAUSE
This behavior may occur when the following conditions are true:
- The Units for the Minor Scale are set to Weeks,
(click the Timescale tab in the Timescale dialog
box).
- The Week Starts On is set to a day later than Tuesday, (click
the Calendar tab in the Options dialog box).
RESOLUTION
To correct this problem, install Microsoft Project 98 for Windows Service
Release 1 (SR-1).
To work around this problem, use either of the following methods.
Method 1: Use a Minor Timescale Unit Other Than Weeks
To change the timescale settings in the Task Usage or Resource Usage view, follow these steps:
- On the Format menu, click Timescale.
- On the Timescale tab, under Minor Scale, click a unit
other than Weeks in the Units list, and then click
OK.
Method 2: Set the Week to Start on Only Sunday, Monday or Tuesday
To change the starting day of the week, follow these steps:
- On the Tools menu, click Options, and then click the
Calendar tab.
- In the Week Starts On list, click the day that you want, and
then click OK.
STATUSMicrosoft has confirmed that this is a problem in the Microsoft products that are listed at the beginning of this article.
This problem was corrected in Microsoft Project 98 for Windows, Service
Release 1 (SR-1).
For additional information about obtaining and installing SR-1, click the
article number below to view the article in the Microsoft Knowledge Base:
185102
PRJ98: How to Obtain and Install MS Project 98 SR-1
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug kbprint KB186072 |
---|
|