PRJ98: Summary Task Cost and Work Not Displayed in Reports (185285)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q185285

SYMPTOMS

In Microsoft Project 98, when you print or print preview a CrossTab report that includes cost or work information, costs or work assigned to summary tasks is not displayed.

CAUSE

Microsoft Project 98 does not display costs or work assigned to summary tasks in reports. This also applies to inserted project summary tasks, and project summary tasks.

RESOLUTION

To correct this problem, install Microsoft Project 98 for Windows Service Release 1 (SR-1).

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:

185102 PRJ98: How to Obtain and Install MS Project 98 SR-1


Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB185285