PRJ98: Unexpected Leveling Delay for Tasks with SNET Constraint (184671)



The information in this article applies to:

  • Microsoft Project 98 for Windows

This article was previously published under Q184671

SYMPTOMS

In Microsoft Project 98, when you level a project, an unexpected delay may occur on tasks with Start No Earlier Than (SNET) constraints.

CAUSE

This behavior occurs when a task has a SNET constraint that is during nonworking time. The leveling delay added to the task includes the nonworking time, which adds more delay to the task than is necessary.

WORKAROUND

To work around this behavior, avoid assigning a task a SNET constraint during nonworking time. Instead, assign SNET constraints during working time.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project 98 for Windows, Service Release 1 (SR-1).

For additional information about obtaining and installing SR-1, click the article number below to view the article in the Microsoft Knowledge Base:

185102 PRJ98: How to Obtain and Install MS Project 98 SR-1


Modification Type:MajorLast Reviewed:10/17/2002
Keywords:kbbug KB184671