PRJ98: Unexpected Assignment Sort Order When Project Exported (182895)
The information in this article applies to:
- Microsoft Project 98 for Windows
This article was previously published under Q182895 SYMPTOMS
In Microsoft Project 98, when you use an export format map to save a file
that contains inserted projects, tasks in the Assignments section are not
grouped by project.
NOTE: One example of an export format map is "Export to HTML using standard template."
CAUSE
When you use an export format map to save a project, tasks in the
Assignments section are sorted by the Unique ID field (not shown by
default), instead of by the Project or Task ID field.
STATUS
Microsoft has confirmed this to be a problem in the versions of Microsoft
Project listed above.
Modification Type: | Major | Last Reviewed: | 10/17/2002 |
---|
Keywords: | kbbug KB182895 |
---|
|