PRJ: Use Default in Change Working Time Dialog Shows Exception (178397)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows

This article was previously published under Q178397

SYMPTOMS

In the Change Working Time dialog box, when you select a column representing a day and then click Use Default, one or more days may unexpectedly be displayed as exceptions, although the working times are correct.

CAUSE

This problem occurs when a task has timephased percent complete that occurs outside of standard working time.

For example, if a task occurs on a Monday from 4:00 AM until 12:00 PM, and the default working time is 8:00 AM to 5:00 PM, that Monday is displayed as exception if you choose the default working times for all Mondays. Note that the working time still reflects 8:00 AM until 5:00 PM.

WORKAROUND

To remove exception indicators, follow these steps:
  1. On the Tools menu, click Change Working Time.
  2. In the Change Working Time dialog box, click to select the day that shows the exception, and then click Use Default. Repeat this step for all days where you want to remove the exception indicators.
NOTE: If you select a column that represents a day of the week, and then click Use Default, some days are again displayed as exceptions, although their working times are correct.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

Modification Type:MinorLast Reviewed:7/27/2006
Keywords:kbbug kbnofix KB178397