How Actual Work Is Calculated When Status Is Set to Complete (159387)



The information in this article applies to:

  • Microsoft Team Manager

This article was previously published under Q159387

SUMMARY

When you change the status to completed in the Task Properties dialog box, Team Manager uses the Reschedule From date and the current system date on the computer to determine how the remaining work should be distributed as actual work across the length of the task. The following scenarios describes how Team Manager uses these dates:

Case 1: No actual work has been applied:

  • If the current date is the same or later than the Reschedule From date for the person, Actual work is applied to the current date. -or-

  • If the current date is earlier than the Reschedule From date, the actual work is applied to the date preceding the Reschedule From date for the person.
Case 2: Some actual work has been applied:

  • If the current date is earlier than the Reschedule From date, the actual work is applied to the date preceding the Reschedule From date for the person. -or-

  • If the current date is the same or later than the Reschedule From date and there is no working time between these date, the actual work is evenly distributed between these dates. -or-

  • If the current date is the same or later than the Reschedule From date and there is one or more working days between these dates, actual work is evenly distributed between the working days of the time period.

MORE INFORMATION

To determine the Reschedule From date for a person, Team Manager calculates the latest date that has actual work applied to the person. This date is incremented 1 day and that becomes the new Reschedule From date for the person. For example if a person has a Reschedule From date of 6/1/96 and 4 hours of actual work is entered for 6/3/96, Team Manager will update the Reschedule From date to 6/4/96.